I arrived on the house plot to find the building team laying out the
interlocking insulation panels, that had been delivered early that
morning, right across the house area.
|
Ready for the insulation layer. |
This insulation was being laid directly upon the main beams layer (see
previous post) and was to then be covered with the first layer of the
concrete slab.
|
Interlocking panels being cut and laid in place. |
This first slab layer needed to be reinforced with the wire mesh that is
seen used everywhere as fencing, forming the structure of small poly
tunnels etc. etc. Therefore when about a third of the insulation had
been laid mesh was laid directly on top of it to hold it in place prior
to the first pour of the concrete.
|
First layer of mesh applied directly upon the insulation. |
|
A rough layer of concrete being laid over the insulation and mesh. |
After this first pour which put down a rough layer of concrete
approximately half the thickness of the planned pour for that day
another layer of reinforcing mesh was laid across the wet concrete,
stamped down into it and then more concrete poured on top to attain the
desired depth. This was then tamped down with the mechanical vibrating
tool and finished by hand to obtain a good level surface.
|
The second layer of mesh being cut and laid onto the rough layer of concrete. |
|
The vibration team goes first followed by the hand tamping and finishing. |
All was going along steadily until the concrete pump and first lorry of
ready mix appeared a little earlier than expected and after a short
delay, whilst the first major section preparation was completed, pouring
started, the second layer of mesh applied and the pouring for that
first area completed, vibrated and carefully finished. Special attention
was again paid by the team to the section around the perimeter of the
house site and this time also to carefully working the concrete around
the reinforced waste pipes to avoid damaging them.
Unfortunately at
this point the team ran out of reinforcing mesh. They seemed very
relaxed about it, despite a partly unloaded ready mix lorry poised to
load the pump and two other lorries waiting further up the plot so I
decided more mesh must be on its way. Sure enough after a very well
earned lunch break a lorry turned up with more mesh, literally dropped
it off the back and rapidly departed.
It was then again like the
starers pistol had been fired with all hands to the pump to get the mesh
in place so that the pour, vibrating and tamping down could continue.
|
The last of the concrete pour, vibration and finishing continuing and the earlier areas being damped down. |
Work then continued uninterrupted until all the insulation, enforcing
mesh and concrete had been poured. The pump and the last lorry departed
leaving the team to finish off. By then it was quite late, had clouded
up and was getting quite dark but had once again been an amazingly
productive day.
|
Finishing off a very productive day. |